Kenya project / UNIDO LCET* Programme
Irrigation canal, MWEA, Kirinyaga district / rated output : 15kW x 2units / Sept. 2015
for details on this project, please refer to the following link : (
UNIDO ULH-MHP PROJECT IN KENYA )
* LCET : Low Carbon Low Emission Clean Energy Technology Transfer Programme for details, please refer to the following link : (
UNIDO LCET PROGRAMME )
Ethiopia project / UNIDO LCET* Programme
Irrigation canal, Fentale, Oromia region / rated output : 30kW / Aug. 2015
* LCET : Low Carbon Low Emission Clean Energy Technology Transfer Programme for details, please refer to the following link : (
UNIDO LCET PROGRAMME )
Myanmar project / Japan’s ODA grants (The Project for Electrification of Rural Villages)
Bypass from river, Taunggyi township, Shan state / rated output : 7.4kW / Oct. 2016
Bypass from river, Lashio township, Shan state / rated output : 7.4kW / Oct. 2016
Vietnam project / JICA programme
Penstock, Tan Lac district, Hoa Binh province / rated output : 22kW / Sept. 2015
India project / UNIDO programme
Irrigation canal, Bahadrabad, Uttarakhand / rated output : 15kW x 2units / Apr. 2015
Korea project / Pilot survey at thermal power plant
Cooling water of thermal power plant, Gyeongnam / rated output : 30kW x 2units / July 2014
India project / UNIDO programme
Irrigation canal, Bahadrabad, Uttarakhand / rated output : 15kW / Mar. 2014
Domestic projects in Japan
Intake of river, Hokkaido Prefectural Enterprise Bureau / rated output : 30kW / Apr. 2019
Irrigation canal (Bypass), Yamagata pref. / rated output : 15kW / Mar. 2018
Irrigation canal, Nagano pref. / rated output : 37kW x 2units / Mar. 2017
Irrigation canal, Nagano pref. / rated output : 37kW x 2units / Mar. 2017
Irrigation canal, Fukushima pref. / rated output : 4.4kW / Mar. 2017
Waterway, Tokushima pref. / rated output : 0.8 kW / Apr. 2016
Sewage treatment plant, Ishikawa pref. / rated output : 4.4 kW / Mar. 2016
Irrigation canal, Nagano pref. / rated output : 37kW x 2units / May 2016
Irrigation canal, Siga pref. / rated output : 15 kW x 2units / Mar. 2015
Bypass from river, Ishikawa pref. / rated output : 3kW / May 2015
Irrigation canal, Miyagi pref. / rated output : 11kW / Mar. 2015
Waterway, Ishikawa pref. / rated output : 1.5kW / Feb. 2014
Sewage treatment plant, Kanagawa pref. / rated output : 4.4kW / Feb. 2014
Irrigation canal, Kanagawa pref. / rated output : 15kW / Mar. 2013
Irrigation canal, Yamanashi pref. / rated output : 4.4kW / Apr. 2013
Irrigation canal, Yamanashi pref. / rated output : 7.4kW / Apr. 2013
Bypass from river / before 2012
Pilot survey / before 2011
Pilot survey / before 2011
Pilot survey / before 2011